Community Projects & Initiatives

Current Projects

  1. Kuna Chambers Build 2025

Kuna Chambers Building 2025

Status: In Progress

Project Start Date: October 6, 2025

Estimated Completion Date: July 18, 2026

Construction Hours: 8:00-5:00 PM

Funding: City Project

Key Features: The new building will include an open Council Chambers with dedicated seating for the Kuna City Council, Directors, and a public gallery. It will feature modern audio-visual systems to enhance transparency and participation, as well as flexible meeting spaces to adapt to our growing community.

Impact: With more people that are now attending City Council meetings and Commission meetings, a space larger than the current Council Chambers can offer is needed to accommodate all attendees. The new Council Chambers will be able to host approximately 250 people.

Completed Projects

  1. Kay & Avalon Signal 2025

Kay & Avalon Signal 2025


Project Start Date: February 10, 2025
Estimated Completion Date: May 31, 2025 
Construction Hours: 7:00 AM - 5:00 PM; striping & energizing of signal to occur during night
Funding: $1.12 million ITD Initiatives Program Grant
Key Features: 4-way stoplight, enhanced pedestrian crossings
Impact: Traffic & pedestrian safety increases with signal

March 31 - April 6
April 7 - April 12
LANE CLOSURE: Right westbound lane closed from N Sunbird Ave to Fiesta Guadalajara; Kay Ave & business access remains
LANE CLOSURE: Right westbound lane closed from N Sunbird Ave to Fiesta Guadalajara; Kay Ave & business access remains
Idaho Power installs electrical serviceIdaho Power, Idaho Transportation Department & Ada County Highway District perform inspections

*Signals go live*

Remove traffic control & pedestrian detour signage

Restore landscaping

Final cleanup & review